http://dapmalaysia.org Forward Feedback
Najib Tun Razak should show leadership by example and take his own advice that ministries must answer fund mismanagement and misuse disclosed in the Auditor-General’s 2006 Report by explaining the RM 6.75 billion scandal of 6 offshore patrol vessels (OPV) that has either not been delivered or not operational ______________ Press Statement
by Lim Guan Eng
__________________
(Petaling Jaya, Monday): Deputy Prime Minister Najib Tun Razak appears to promote transparency, accountability and good governance by demanding that Ministries must answer for the instances of mismanagement disclosed in the Auditor-General’s 2006 Report released in Parliament last week. Najib was referring to glaring cases highlighted in the Report involved the Youth and Sports Ministry which said the government paid RM 8.39 million more than the market price in 2002 for the purchase of 13 items for the National Youth Skills Institutes (NYSI) programme, such as :-
These widespread abuses of public funds in the NYSI are only a tip of iceberg as there are many other cases of misuse of public funds outlined in the 2006 Auditor-General’s report. As Minister, Datuk Azlina Othman must get to the bottom of this scandal explain why their spendings were not in order, and take action against errant officials to demonstrate that she is not involved in this shameful scandal. On the other hand, Najib should show leadership by example and take his own advice that Ministries must answer fund mismanagement and misuse disclosed in the Auditor-General’s 2006 Report by explaining the RM 6.75 billion scandal of 6 Offshore Patrol Vessels(OPV) that has either not been delivered or not operational. Najib must explain why the contract price was allowed to increase twice from RM 4.9 billion to RM 6.75 billion or 38 % even though the OPVs were either not delivered or not operational The RM 6.75 billion OPV scandal is the largest single case of misuse of funds in the 2006 Auditor-General’s Report. 6 OPVs were ordered initially at RM 4.9 billion. This was subsequently increased to RM 5.35 billion in September 1998. All the 6 OPVs were supposed to be delivered by April 2007 with the first delivery on March 2004. However only 2 OPVs were delivered so far and the 2 OPVs are not fully operational as the technical specifications required are still not completely performed. A penalty of 0.5% per month based on the contract value is imposed for any delay. However such penalties can not exceed RM 53.5 million, a very generous self-imposed limit by the government. The first OPV was late by 27 months and the second OPV was late by 18 months but yet both are imposed penalties of RM 53.5 million each due to the self-imposed limit. The other four OPVs are still not delivered. The Auditor-General Report estimated that the government can claim at least RM 214 million in late penalties for the late delivery of the 2 OPVs and nopn-delivery of the remaining 4 OPVs. However in another remarkable and unwarranted act of charity and generosity, the Cabinet on 29.11.2006 waived the claim of penalties. Worse, in a continuing act of generosity and charity the government increased the contract price by RM 1.4 billion in January 2007. The cost for the 6 OPVs had risen by RM 1.85 billion or 38% from the original contract price of RM 4.9 billion to RM 6.75 billion, ie to RM 5.35 billion in September 1998 and again to RM 6.75 billion in January 2007. Najib must explain why the contract price was allowed to increase twice from RM 4.9 billion to RM 6.75 billion or 38 % even though the OPVs were either not delivered or not operational. Najib must also explain why the government surrendered and waived its claim for late penalties of RM 214 million. More importantly why is the government continuing to throw money to the contractor even though they have failed to perform and deliver on their contracts. The most shocking aspect about this RM 6.75 billion scandal that Najib must answer is why did the Defence Ministry pay in advance RM 4.26 billion to the contractor by 31.12.2006, even though progress of work done only amounts to RM 2.87 billion. Would not the government lose RM 1.4 billion should the contractor abscond? Such behaviour is not only reckless, imprudent but also irresponsible. A full-fledged enquiry is necessary as to how RM 6.75 billion could be lost to purchase OPVs for the defence of our naval waters that would either not be delivered or not fully operational.
(10 /9/2007)
* Lim Guan Eng, Secretary-General of DAP |