Is Trans Sabah Gas Pipeline feasible?

The announcement by a Minister in the Prime Minister’s Department on the Trans Sabah Gas Pipeline (TSGP) supposedly to refute allegation that the Prime Minister collateralised oil and gas blocks off Sabah to China for a loan of RM100 billion has raised more questions instead.

Datuk Abdul Rahman Dahlan’s had announced that the TSGP will be funded by a soft loan of RM4.53 billion from the Export and Import Bank of China (EIBC) and guaranteed by the Malaysian government but this did not clear the air.

DAP Sabah’s concern was first, “where is the feasibility study of the TSGP?”

If the Labuan-Menumbok Bridge which is to cost RM3 billion to RM6 billion needs a RM14 million budget to conduct a techno-economic feasibility study, why shouldn’t the government do the same kind of study on the TSGP which costs RM4.53 billion?

Is it feasible to construct the natural gas pipeline from Kimanis which would pass through forest, oil palm plantation before landing at Sandakan?

How much land cost involved in the project as compensation needed? Would it be time consuming in taking over the land?

Secondly, why should the owner-cum-developer of the TSGP, Suria Strategic Energy Resources Sdn Bhd (SSER), a Government-Linked-Company (GLC) owned by Malaysia’s Ministry of Finance, borrow soft loan from China, with Malaysian government as guarantor?

Why couldn’t we look for a Private Finance Initiative (PFI) option for this project? Eventually who pay for the RM4.53 billion soft loan? Federal Government or Sabah electricity consumer?

How much the interest? How long the repayment period? Would the electricity tariff in Sabah increased to compensate any losses made by the project?

Why couldn’t Petronas pay for the TSGP construction, as what they did for the Sabah Sarawak Gas Pipeline (SSGP) which started from Kimanis and ended at Bintulu?

We the People have the right to know the truth!

Thirdly, how many years are needed to construct the TSGP until its commissioning?

If the SSGP with similar size (RM4.6 billion and 500km) have taken four years (2011 to 2014) to complete, it is safe to estimate that the TSGP would be ready to operate in 2022.

The Natural Gas power plant is yet to be built or announced to be built while at time being, it would take another three years to construct an anchor power plant in Sandakan.

Would it be too late for the East Coast of Sabah to catch up with the energy shortage? Why couldn’t we aim for faster option to meet the energy demand in East Coast?

Renewables, such as solar, biomass and biogas (East Coast of Sabah full with big oil palm plantations), should be the option, an anchor power plant with at least 300MW power generation is long overdue since the proposed coal fired power plant called off in 2007.

There has been no new development as far as energy generation in the East Coast is concerned, particularly after the proposed Liquified Natural Gas power plant in Palm Oil Industrial Cluster, Lahad Datu was scrapped when the Sulu invasion happened in 2013.

Now, the general election is just around the corner but East Coast of Sabah still suffers with negative power reserves.

Can the Barisan Nasional government put in effort and make real things happen, without compromising the public interest?

Malaysian government guaranteed kind of project, just really sounds like the scandalous 1MDB!